Cappa CM were engaged to complete remediation works to two Water Recycling Tanks in South-West Sydney. Cappa utilised two Putzmeister S5 EVTM and two spray crews to spray over 50,000 litres of repair material. The tanks consisted of a mixture of 5.2m high walls, columns, and soffits, requiring the team to access areas using EWPs. We deployed two spray crews, a total of 16 men to follow our client's programme. Due to the project taking place on a Sydney Water site, strict adherence to quality and safety guidelines was required at all times, with Cappa effectively managing all elements of HSEQ.