Replaced 22 structural steel columns at 10 metre lengths
All works were completed across 6 working weeks
Liaised with ACT Fire and Rescue to ensure all works were completed in accordance with regulations
Cappa CM was engaged by their client BIM to replace all columns inside a Woolworth distribution centre in ACT.
Scope of works included full warehouse propping to allow for the removal and replacement of columns, excavation, and completion of pad footings for column installation and finally installing twenty-two, ten-metre- long columns.